City bus stand development
Amount: 32.23 Crores
Period of Work: 24 Months
Contractor: Apoorva Construction co Tumkur
Basement + 5 floors Parking for 89 cars and 72 Two wheelers
Bus Bays: 28 Lifts: 4 Escalators: 3
Subway connection to Central Bus Stand
7 Roads in Ramtirth Nagar – 24.03 Crore
RTO Office to Jija Mata Chowk, Market Police Station, Vegetable Market Road, Circuit House Road – 34.03 Crore
CBT to Hotel Surabahi road – Footpath and Cycle Track – 6.12 Crore
12 months
35 Smart Bus Shelter – 6.54 Crore
UG LT cabling Mahantesh Nagar, SriNagar, Anjaneya Nagar – 22.17 Crore
Private Bus Parking – 1.96 crore
Opposite Railway Station
SOUHARDHA INFRA-TECH PRIVATE LIMITED
9 Months
Development of Kalamandir – 46.68 Crore
Contractor: Yankee Construction Bengaluru
Completion date: Feb 2021
basement+Ground+2 floors, where the second floor will have a Multiplex.
Basement: Car Parking
Ground Floor: Shops
First Floor: Shops & Food Court
Second Floor: Meeting Hall Lobby, Multiplex which will have a steel roof
Smart Road Package 4 – 34.03 Crore
Kapileshwar Colony Road, SPM Road, Mahatma Phule Road, Shukurwar Peth and others
Road Length: 5.35 Km
Completion date: Feb 2020
Smart Road Package 5 – 37.96 Crore
Congress Road
Road Length: 5.65 Km
Heritage Park Phase 2 – 18.61 Crore
Completion date: 13-11-2019
Smart bus shelter Phase 2 & 3 –
The post 264.36 crore worth works started under Smart city today appeared first on All About Belgaum.