In January 2016, Belagavi was selected in the first 20 cities which were to become Smart under the Ambitious smart city project.
Here is a list of projects undertaken under the Belagavi smart city project and its current status.
We will try and update this frequently so that one can stay informed about how the projects are been executed.
Works commenced- 471 crores
231 crores worth work is tendered and work would start in the next 3 months positively
Sl No. | Project Details | Cost in Crores | Status |
1 | Smart Roads – KPTCL and Mandoli Road | 22.4 | KPTCL Road- Road Work- GSB work in progress, RCC Drain, Duct, Gas Pipeline Completed Mandoli Road- Ducting: 730 Mtrs completed, Drain 80% completed, Footpath and road work under progress |
2 | Heritage Park Phase 1 | 4.27 | Check Weir: 5 Mtrs height Bodywal and side walls completed Check Weir2: 3 mtr height, weir portion completed, apron wall under Progress |
3 | System Integrator for Common Command centre | 45.99 | First Milestone Approved on 1-2-19. Procurement of Materials under progress |
4 | Command and control Centre building | 2.99 | Flooring Complete,finishing work in progress |
5 | road side Drinking Water Kiosks Phase 1 | 0.38 | Work Completed |
6 | Rehabilitation of Stray Cattle | 0.64 | Main Structure near completetion, |
7 | Smart Bus Shelter with bus bay | 1.91 | Flooring and Paving completed |
8 | Rainwater harvesting and compositing facility in Parks | 0.08 | Completed |
9 | Smart roads -Dharmanath Bhavan Area | 43.64 | UG ducting, Storm water drain in progress |
10 | City Bus Terminal | 32.23 | Dismantling of Exisiting buuilding compeleted |
11 | Theme Based Park- Nath Pai Garden | 0.924 | Work nearing completetion |
12 | Kanbargi Lake rejuvenations | 4.47 | Drain Slab Completed, allied work under progress |
13 | 30 bed hospital at Vantmuri | 2.33 | Work compeleted upto Plinth level |
14 | Smart roads – Sri Nagar | 43.58 | UG ducting, Storm water drain in progress |
15 | Smart roads -Shahpur Area | 34.03 | UG ducting, Storm water drain in progress |
16 | Smart Roads- Congress road, | 37.96 | Drain Work in progress |
17 | UG LT Cabling Sri nagar | 7.19 | Procurement of Cable under Progress |
18 | UG LT Cabling Mahantesh Nagar | 6.7 | Procurement of Cable under Progress |
19 | UG LT Cabling Anjanaey Nagar | 8.27 | Procurement of Cable under Progress |
20 | Smart Bus Shelter Phase 3 | Work Order Issued | |
21 | Smart Bus Shelter Phase 2 | 4.8 | Under progress |
22 | Digital Board | 0.71 | Under progress |
23 | Smart Bus Shelter Phase 3 | 1.74 | Work Order Issued |
24 | Procurement of Traffic Signals | 1.7 | Work Order Issued |
25 | Construction of Cycle Track – Ashoka circle to Hotel Surabhi | 6.13 | Work Order Issued |
26 | Heritage Park Phase 2 | 18.62 | Work Order Issued |
27 | Parking for Private Buses opp Railway station | 1.96 | Work Order Issued |
28 | Development of Kalamandir Tilakwadi | 46.69 | Work Order Issued |
29 | Smart Road Ramteerth nagar | 23.3 | Work Order Issued |
30 | Smart Class room Phase 1 | 3.36 | Work Order Issued |
31 | Taruma Centre | Tender Floated | |
32 | Road side Drinking Water Kiosks Phase 2 | Tender Floated | |
33 | White Topping of Roads – KLE Hospital to Rani Chennamma circle, and Sangollli Rayana Circle | Tender Floated | |
34 | White Topping of Roads – BOI circle Nath Pai Circle shahpur, Navhind Society, Rpd Cross, First gate to Swimming Pool | Tender Floated | |
35 | White Topping of Roads – Bank of India to Old PB Road, APMC to Kangrali | Tender Floated | |
36 | Construction of Cycle Track/Footpath –Bauxite road to Ganesh Temple via Hanuman Nagar circle upto KLE School | Tender Floated | |
37 | Construction of Cycle Track/Footpath –APMC junction to Azam Nagar further upto Inmark showroom | Tender Floated | |
38 | Construction of Cycle Track/Footpath – Chennamma Nagar and Tilakwadi Area | Tender Floated | |
39 | UG LT Cabling Shanti Nagar Shivaji Colony | Tender Floated | |
40 | UG LT Cabling Maratha Colony Nanawadi | Tender Floated | |
41 | UG LT Cabling First gate | Tender Floated | |
42 | UG LT Cabling Shkurwar Peth, Mahatma Phule road | Tender Floated | |
43 | UG LT Cabling SPM Road, Shahstri Nagar | Tender Floated | |
44 | Development of Mahatma Phule Garden Tilakwadi | Tender Floated | |
45 | Smart Class Phase 3 | Tender Floated | |
46 | 10 Bed Hospital at Vadgaon | Tender Floated |
The post Belagavi Smart City Progress Report – 471 Crores works commenced appeared first on All About Belgaum.